Order · SC-2404
Anglian Water Bedford WwTW
Anglian Water Services · Start 2025-09-04 · FAT 2026-05-20 · Delivery 2026-06-12
Status
delayed
Contract value
£0.98M
Forecast margin
12.5%
Panels
22
2 switchboards
Stages complete
177/396
7 blocked
Project Hierarchy
Switchboard → Panel Type → Panel → Current Stage. Click a panel to open its lifecycle.
MCC-Inlet
12 panels · 2 types
Pump Starter · 8/8
Instrument · 4/4
MCC-Aeration
10 panels · 1 types
VSD Drawer · 10/10
Delivery Rollup
Avg completion45%
Avg panel health72%
Milestones48
Open risks5
Open issues6
Variations5
Commercial Snapshot
Labour budget£343,000
Labour actual£281,208
Labour variance£61,792
Material budget£441,000
Material actual£188,538
Material variance£252,462
WIP£509,414
Earned progress63%
Procurement (P1–P9)
P1Long Lead Approval Items97/159
P2Steelwork97/149
P3Copper169/205
P4Major Components139/192
P5Labels115/132
P6Cable Identification19/44
P7OEM Equipment80/172
P8Terminals & Wiring Accessories65/70
P9Specialist Items66/79
Quality Gates (QG1–QG7)
QG1Project Handoverpassed
QG2Engineering Releasepassed
QG3Incoming Materials Inspectionpassed
QG4Manufacturing Releasein-review
QG5In-Process Manufacturing Inspectionpending
QG6Pre-FAT Approvalpending
QG7FAT & Shipment Releasepending