Programme

Milestone Tracker

Estimated vs actual milestone dates with variance days, dependency/blocker, owner and recovery action. Click any cell to edit.

Tracked Milestones
192
Green
68
Amber
32
Red
92
SC-2401 · Heathrow T2 LV Distribution
PanelMilestoneEstimatedActualVar (d)RAGBlockerOwnerRecovery
MSB-01-INC-01Pre Design2026-02-052026-02-13+8RedAwaiting client approvalProduction ManagerExpedite supplier / reallocate labour
MSB-01-INC-01Design & Approvals2026-03-082026-03-09+1Amber—M. HendersonExpedite supplier / reallocate labour
MSB-01-INC-01Procurement2026-04-112026-04-14+3Amber—Brendan BegleyExpedite supplier / reallocate labour
MSB-01-INC-01Stores2026-05-14—-2Green—M. Henderson—
MSB-01-INC-01Production2026-06-17—-2Green—Procurement—
MSB-01-INC-01Testing (PDI/FAT)2026-07-20—+7RedAwaiting client approvalOisin LeonardExpedite supplier / reallocate labour
MSB-01-INC-02Pre Design2026-02-052026-02-05-1Green—Oisin Leonard—
MSB-01-INC-02Design & Approvals2026-03-082026-03-15+7RedAwaiting client approvalM. HendersonExpedite supplier / reallocate labour
MSB-01-INC-02Procurement2026-04-112026-04-17+6RedAwaiting client approvalBrendan BegleyExpedite supplier / reallocate labour
MSB-01-INC-02Stores2026-05-14—+1Amber—Oisin LeonardExpedite supplier / reallocate labour
MSB-01-INC-02Production2026-06-17—+5RedAwaiting client approvalProduction ManagerExpedite supplier / reallocate labour
MSB-01-INC-02Testing (PDI/FAT)2026-07-20—+5RedAwaiting client approvalProduction ManagerExpedite supplier / reallocate labour
MSB-01-BUS-01Pre Design2026-02-052026-02-05-5Green—Production Manager—
MSB-01-BUS-01Design & Approvals2026-03-082026-03-08-4Green—M. Henderson—
MSB-01-BUS-01Procurement2026-04-112026-04-11-5Green—Production Manager—
MSB-01-BUS-01Stores2026-05-14—0Green—M. Henderson—
MSB-01-BUS-01Production2026-06-17—0Green—M. Henderson—
MSB-01-BUS-01Testing (PDI/FAT)2026-07-20—+7RedAwaiting client approvalOisin LeonardExpedite supplier / reallocate labour
MSB-01-OUT-01Pre Design2026-02-052026-02-12+7RedAwaiting client approvalM. HendersonExpedite supplier / reallocate labour
MSB-01-OUT-01Design & Approvals2026-03-082026-03-15+7RedAwaiting client approvalBrendan BegleyExpedite supplier / reallocate labour
MSB-01-OUT-01Procurement2026-04-112026-04-17+6RedAwaiting client approvalProcurementExpedite supplier / reallocate labour
MSB-01-OUT-01Stores2026-05-14—+5RedAwaiting client approvalBrendan BegleyExpedite supplier / reallocate labour
MSB-01-OUT-01Production2026-06-17—+8RedAwaiting client approvalBrendan BegleyExpedite supplier / reallocate labour
MSB-01-OUT-01Testing (PDI/FAT)2026-07-20—-5Green—Oisin Leonard—
MSB-01-OUT-02Pre Design2026-02-052026-02-06+1Amber—Production ManagerExpedite supplier / reallocate labour
MSB-01-OUT-02Design & Approvals2026-03-082026-03-15+7RedAwaiting client approvalOisin LeonardExpedite supplier / reallocate labour
MSB-01-OUT-02Procurement2026-04-112026-04-18+7RedAwaiting client approvalOisin LeonardExpedite supplier / reallocate labour
MSB-01-OUT-02Stores2026-05-14—-3Green—Procurement—
MSB-01-OUT-02Production2026-06-17—-6Green—M. Henderson—
MSB-01-OUT-02Testing (PDI/FAT)2026-07-20—+6RedAwaiting client approvalOisin LeonardExpedite supplier / reallocate labour
MSB-01-OUT-03Pre Design2026-02-052026-02-050Green—M. Henderson—
MSB-01-OUT-03Design & Approvals2026-03-082026-03-12+4RedAwaiting client approvalM. HendersonExpedite supplier / reallocate labour
MSB-01-OUT-03Procurement2026-04-112026-04-19+8RedAwaiting client approvalM. HendersonExpedite supplier / reallocate labour
MSB-01-OUT-03Stores2026-05-14—0Green—Brendan Begley—
MSB-01-OUT-03Production2026-06-17—-2Green—Brendan Begley—
MSB-01-OUT-03Testing (PDI/FAT)2026-07-20—+6RedAwaiting client approvalOisin LeonardExpedite supplier / reallocate labour
MSB-01-OUT-04Pre Design2026-02-052026-02-06+1Amber—Production ManagerExpedite supplier / reallocate labour
MSB-01-OUT-04Design & Approvals2026-03-082026-03-08-5Green—M. Henderson—
MSB-01-OUT-04Procurement2026-04-112026-04-15+4RedAwaiting client approvalProduction ManagerExpedite supplier / reallocate labour
MSB-01-OUT-04Stores2026-05-14—+8RedAwaiting client approvalM. HendersonExpedite supplier / reallocate labour
MSB-01-OUT-04Production2026-06-17—-1Green—Brendan Begley—
MSB-01-OUT-04Testing (PDI/FAT)2026-07-20—+6RedAwaiting client approvalProcurementExpedite supplier / reallocate labour
MSB-01-OUT-05Pre Design2026-02-052026-02-05-2Green—Brendan Begley—
MSB-01-OUT-05Design & Approvals2026-03-082026-03-10+2Amber—Production ManagerExpedite supplier / reallocate labour
MSB-01-OUT-05Procurement2026-04-112026-04-15+4RedAwaiting client approvalBrendan BegleyExpedite supplier / reallocate labour
MSB-01-OUT-05Stores2026-05-14—+3Amber—Brendan BegleyExpedite supplier / reallocate labour
MSB-01-OUT-05Production2026-06-17—+8RedAwaiting client approvalProcurementExpedite supplier / reallocate labour
MSB-01-OUT-05Testing (PDI/FAT)2026-07-20—+1Amber—Oisin LeonardExpedite supplier / reallocate labour
SC-2402 · Sellafield Process Control Suite
PanelMilestoneEstimatedActualVar (d)RAGBlockerOwnerRecovery
PLC-Cab-PLC-01Pre Design2026-02-052026-02-13+8RedAwaiting client approvalProduction ManagerExpedite supplier / reallocate labour
PLC-Cab-PLC-01Design & Approvals2026-03-082026-03-09+1Amber—M. HendersonExpedite supplier / reallocate labour
PLC-Cab-PLC-01Procurement2026-04-112026-04-14+3Amber—Brendan BegleyExpedite supplier / reallocate labour
PLC-Cab-PLC-01Stores2026-05-14—-2Green—M. Henderson—
PLC-Cab-PLC-01Production2026-06-17—-2Green—Procurement—
PLC-Cab-PLC-01Testing (PDI/FAT)2026-07-20—+7RedAwaiting client approvalOisin LeonardExpedite supplier / reallocate labour
PLC-Cab-PLC-02Pre Design2026-02-052026-02-05-1Green—Oisin Leonard—
PLC-Cab-PLC-02Design & Approvals2026-03-082026-03-15+7RedAwaiting client approvalM. HendersonExpedite supplier / reallocate labour
PLC-Cab-PLC-02Procurement2026-04-112026-04-17+6RedAwaiting client approvalBrendan BegleyExpedite supplier / reallocate labour
PLC-Cab-PLC-02Stores2026-05-14—+1Amber—Oisin LeonardExpedite supplier / reallocate labour
PLC-Cab-PLC-02Production2026-06-17—+5RedAwaiting client approvalProduction ManagerExpedite supplier / reallocate labour
PLC-Cab-PLC-02Testing (PDI/FAT)2026-07-20—+5RedAwaiting client approvalProduction ManagerExpedite supplier / reallocate labour
PLC-Cab-PLC-03Pre Design2026-02-052026-02-05-5Green—Production Manager—
PLC-Cab-PLC-03Design & Approvals2026-03-082026-03-08-4Green—M. Henderson—
PLC-Cab-PLC-03Procurement2026-04-112026-04-11-5Green—Production Manager—
PLC-Cab-PLC-03Stores2026-05-14—0Green—M. Henderson—
PLC-Cab-PLC-03Production2026-06-17—0Green—M. Henderson—
PLC-Cab-PLC-03Testing (PDI/FAT)2026-07-20—+7RedAwaiting client approvalOisin LeonardExpedite supplier / reallocate labour
PLC-Cab-PLC-04Pre Design2026-02-052026-02-12+7RedAwaiting client approvalM. HendersonExpedite supplier / reallocate labour
PLC-Cab-PLC-04Design & Approvals2026-03-082026-03-15+7RedAwaiting client approvalBrendan BegleyExpedite supplier / reallocate labour
PLC-Cab-PLC-04Procurement2026-04-112026-04-17+6RedAwaiting client approvalProcurementExpedite supplier / reallocate labour
PLC-Cab-PLC-04Stores2026-05-14—+5RedAwaiting client approvalBrendan BegleyExpedite supplier / reallocate labour
PLC-Cab-PLC-04Production2026-06-17—+8RedAwaiting client approvalBrendan BegleyExpedite supplier / reallocate labour
PLC-Cab-PLC-04Testing (PDI/FAT)2026-07-20—-5Green—Oisin Leonard—
PLC-Cab-MAR-01Pre Design2026-02-052026-02-06+1Amber—Production ManagerExpedite supplier / reallocate labour
PLC-Cab-MAR-01Design & Approvals2026-03-082026-03-15+7RedAwaiting client approvalOisin LeonardExpedite supplier / reallocate labour
PLC-Cab-MAR-01Procurement2026-04-112026-04-18+7RedAwaiting client approvalOisin LeonardExpedite supplier / reallocate labour
PLC-Cab-MAR-01Stores2026-05-14—-3Green—Procurement—
PLC-Cab-MAR-01Production2026-06-17—-6Green—M. Henderson—
PLC-Cab-MAR-01Testing (PDI/FAT)2026-07-20—+6RedAwaiting client approvalOisin LeonardExpedite supplier / reallocate labour
PLC-Cab-MAR-02Pre Design2026-02-052026-02-050Green—M. Henderson—
PLC-Cab-MAR-02Design & Approvals2026-03-082026-03-12+4RedAwaiting client approvalM. HendersonExpedite supplier / reallocate labour
PLC-Cab-MAR-02Procurement2026-04-112026-04-19+8RedAwaiting client approvalM. HendersonExpedite supplier / reallocate labour
PLC-Cab-MAR-02Stores2026-05-14—0Green—Brendan Begley—
PLC-Cab-MAR-02Production2026-06-17—-2Green—Brendan Begley—
PLC-Cab-MAR-02Testing (PDI/FAT)2026-07-20—+6RedAwaiting client approvalOisin LeonardExpedite supplier / reallocate labour
PLC-Cab-PLC-01Pre Design2026-02-052026-02-06+1Amber—Production ManagerExpedite supplier / reallocate labour
PLC-Cab-PLC-01Design & Approvals2026-03-082026-03-08-5Green—M. Henderson—
PLC-Cab-PLC-01Procurement2026-04-112026-04-15+4RedAwaiting client approvalProduction ManagerExpedite supplier / reallocate labour
PLC-Cab-PLC-01Stores2026-05-14—+8RedAwaiting client approvalM. HendersonExpedite supplier / reallocate labour
PLC-Cab-PLC-01Production2026-06-17—-1Green—Brendan Begley—
PLC-Cab-PLC-01Testing (PDI/FAT)2026-07-20—+6RedAwaiting client approvalProcurementExpedite supplier / reallocate labour
PLC-Cab-PLC-02Pre Design2026-02-052026-02-05-2Green—Brendan Begley—
PLC-Cab-PLC-02Design & Approvals2026-03-082026-03-10+2Amber—Production ManagerExpedite supplier / reallocate labour
PLC-Cab-PLC-02Procurement2026-04-112026-04-15+4RedAwaiting client approvalBrendan BegleyExpedite supplier / reallocate labour
PLC-Cab-PLC-02Stores2026-05-14—+3Amber—Brendan BegleyExpedite supplier / reallocate labour
PLC-Cab-PLC-02Production2026-06-17—+8RedAwaiting client approvalProcurementExpedite supplier / reallocate labour
PLC-Cab-PLC-02Testing (PDI/FAT)2026-07-20—+1Amber—Oisin LeonardExpedite supplier / reallocate labour
SC-2403 · Battersea Power Station Phase 3
PanelMilestoneEstimatedActualVar (d)RAGBlockerOwnerRecovery
LV-Switch-01-ACB-01Pre Design2026-02-052026-02-13+8RedAwaiting client approvalProduction ManagerExpedite supplier / reallocate labour
LV-Switch-01-ACB-01Design & Approvals2026-03-082026-03-09+1Amber—M. HendersonExpedite supplier / reallocate labour
LV-Switch-01-ACB-01Procurement2026-04-112026-04-14+3Amber—Brendan BegleyExpedite supplier / reallocate labour
LV-Switch-01-ACB-01Stores2026-05-14—-2Green—M. Henderson—
LV-Switch-01-ACB-01Production2026-06-17—-2Green—Procurement—
LV-Switch-01-ACB-01Testing (PDI/FAT)2026-07-20—+7RedAwaiting client approvalOisin LeonardExpedite supplier / reallocate labour
LV-Switch-01-ACB-02Pre Design2026-02-052026-02-05-1Green—Oisin Leonard—
LV-Switch-01-ACB-02Design & Approvals2026-03-082026-03-15+7RedAwaiting client approvalM. HendersonExpedite supplier / reallocate labour
LV-Switch-01-ACB-02Procurement2026-04-112026-04-17+6RedAwaiting client approvalBrendan BegleyExpedite supplier / reallocate labour
LV-Switch-01-ACB-02Stores2026-05-14—+1Amber—Oisin LeonardExpedite supplier / reallocate labour
LV-Switch-01-ACB-02Production2026-06-17—+5RedAwaiting client approvalProduction ManagerExpedite supplier / reallocate labour
LV-Switch-01-ACB-02Testing (PDI/FAT)2026-07-20—+5RedAwaiting client approvalProduction ManagerExpedite supplier / reallocate labour
LV-Switch-01-MCC-01Pre Design2026-02-052026-02-05-5Green—Production Manager—
LV-Switch-01-MCC-01Design & Approvals2026-03-082026-03-08-4Green—M. Henderson—
LV-Switch-01-MCC-01Procurement2026-04-112026-04-11-5Green—Production Manager—
LV-Switch-01-MCC-01Stores2026-05-14—0Green—M. Henderson—
LV-Switch-01-MCC-01Production2026-06-17—0Green—M. Henderson—
LV-Switch-01-MCC-01Testing (PDI/FAT)2026-07-20—+7RedAwaiting client approvalOisin LeonardExpedite supplier / reallocate labour
LV-Switch-01-MCC-02Pre Design2026-02-052026-02-12+7RedAwaiting client approvalM. HendersonExpedite supplier / reallocate labour
LV-Switch-01-MCC-02Design & Approvals2026-03-082026-03-15+7RedAwaiting client approvalBrendan BegleyExpedite supplier / reallocate labour
LV-Switch-01-MCC-02Procurement2026-04-112026-04-17+6RedAwaiting client approvalProcurementExpedite supplier / reallocate labour
LV-Switch-01-MCC-02Stores2026-05-14—+5RedAwaiting client approvalBrendan BegleyExpedite supplier / reallocate labour
LV-Switch-01-MCC-02Production2026-06-17—+8RedAwaiting client approvalBrendan BegleyExpedite supplier / reallocate labour
LV-Switch-01-MCC-02Testing (PDI/FAT)2026-07-20—-5Green—Oisin Leonard—
LV-Switch-01-MCC-03Pre Design2026-02-052026-02-06+1Amber—Production ManagerExpedite supplier / reallocate labour
LV-Switch-01-MCC-03Design & Approvals2026-03-082026-03-15+7RedAwaiting client approvalOisin LeonardExpedite supplier / reallocate labour
LV-Switch-01-MCC-03Procurement2026-04-112026-04-18+7RedAwaiting client approvalOisin LeonardExpedite supplier / reallocate labour
LV-Switch-01-MCC-03Stores2026-05-14—-3Green—Procurement—
LV-Switch-01-MCC-03Production2026-06-17—-6Green—M. Henderson—
LV-Switch-01-MCC-03Testing (PDI/FAT)2026-07-20—+6RedAwaiting client approvalOisin LeonardExpedite supplier / reallocate labour
LV-Switch-01-MCC-04Pre Design2026-02-052026-02-050Green—M. Henderson—
LV-Switch-01-MCC-04Design & Approvals2026-03-082026-03-12+4RedAwaiting client approvalM. HendersonExpedite supplier / reallocate labour
LV-Switch-01-MCC-04Procurement2026-04-112026-04-19+8RedAwaiting client approvalM. HendersonExpedite supplier / reallocate labour
LV-Switch-01-MCC-04Stores2026-05-14—0Green—Brendan Begley—
LV-Switch-01-MCC-04Production2026-06-17—-2Green—Brendan Begley—
LV-Switch-01-MCC-04Testing (PDI/FAT)2026-07-20—+6RedAwaiting client approvalOisin LeonardExpedite supplier / reallocate labour
LV-Switch-01-MCC-05Pre Design2026-02-052026-02-06+1Amber—Production ManagerExpedite supplier / reallocate labour
LV-Switch-01-MCC-05Design & Approvals2026-03-082026-03-08-5Green—M. Henderson—
LV-Switch-01-MCC-05Procurement2026-04-112026-04-15+4RedAwaiting client approvalProduction ManagerExpedite supplier / reallocate labour
LV-Switch-01-MCC-05Stores2026-05-14—+8RedAwaiting client approvalM. HendersonExpedite supplier / reallocate labour
LV-Switch-01-MCC-05Production2026-06-17—-1Green—Brendan Begley—
LV-Switch-01-MCC-05Testing (PDI/FAT)2026-07-20—+6RedAwaiting client approvalProcurementExpedite supplier / reallocate labour
LV-Switch-01-MCC-06Pre Design2026-02-052026-02-05-2Green—Brendan Begley—
LV-Switch-01-MCC-06Design & Approvals2026-03-082026-03-10+2Amber—Production ManagerExpedite supplier / reallocate labour
LV-Switch-01-MCC-06Procurement2026-04-112026-04-15+4RedAwaiting client approvalBrendan BegleyExpedite supplier / reallocate labour
LV-Switch-01-MCC-06Stores2026-05-14—+3Amber—Brendan BegleyExpedite supplier / reallocate labour
LV-Switch-01-MCC-06Production2026-06-17—+8RedAwaiting client approvalProcurementExpedite supplier / reallocate labour
LV-Switch-01-MCC-06Testing (PDI/FAT)2026-07-20—+1Amber—Oisin LeonardExpedite supplier / reallocate labour
SC-2404 · Anglian Water Bedford WwTW
PanelMilestoneEstimatedActualVar (d)RAGBlockerOwnerRecovery
MCC-Inlet-PUM-01Pre Design2026-02-052026-02-13+8RedAwaiting client approvalProduction ManagerExpedite supplier / reallocate labour
MCC-Inlet-PUM-01Design & Approvals2026-03-082026-03-09+1Amber—M. HendersonExpedite supplier / reallocate labour
MCC-Inlet-PUM-01Procurement2026-04-112026-04-14+3Amber—Brendan BegleyExpedite supplier / reallocate labour
MCC-Inlet-PUM-01Stores2026-05-14—-2Green—M. Henderson—
MCC-Inlet-PUM-01Production2026-06-17—-2Green—Procurement—
MCC-Inlet-PUM-01Testing (PDI/FAT)2026-07-20—+7RedAwaiting client approvalOisin LeonardExpedite supplier / reallocate labour
MCC-Inlet-PUM-02Pre Design2026-02-052026-02-05-1Green—Oisin Leonard—
MCC-Inlet-PUM-02Design & Approvals2026-03-082026-03-15+7RedAwaiting client approvalM. HendersonExpedite supplier / reallocate labour
MCC-Inlet-PUM-02Procurement2026-04-112026-04-17+6RedAwaiting client approvalBrendan BegleyExpedite supplier / reallocate labour
MCC-Inlet-PUM-02Stores2026-05-14—+1Amber—Oisin LeonardExpedite supplier / reallocate labour
MCC-Inlet-PUM-02Production2026-06-17—+5RedAwaiting client approvalProduction ManagerExpedite supplier / reallocate labour
MCC-Inlet-PUM-02Testing (PDI/FAT)2026-07-20—+5RedAwaiting client approvalProduction ManagerExpedite supplier / reallocate labour
MCC-Inlet-PUM-03Pre Design2026-02-052026-02-05-5Green—Production Manager—
MCC-Inlet-PUM-03Design & Approvals2026-03-082026-03-08-4Green—M. Henderson—
MCC-Inlet-PUM-03Procurement2026-04-112026-04-11-5Green—Production Manager—
MCC-Inlet-PUM-03Stores2026-05-14—0Green—M. Henderson—
MCC-Inlet-PUM-03Production2026-06-17—0Green—M. Henderson—
MCC-Inlet-PUM-03Testing (PDI/FAT)2026-07-20—+7RedAwaiting client approvalOisin LeonardExpedite supplier / reallocate labour
MCC-Inlet-PUM-04Pre Design2026-02-052026-02-12+7RedAwaiting client approvalM. HendersonExpedite supplier / reallocate labour
MCC-Inlet-PUM-04Design & Approvals2026-03-082026-03-15+7RedAwaiting client approvalBrendan BegleyExpedite supplier / reallocate labour
MCC-Inlet-PUM-04Procurement2026-04-112026-04-17+6RedAwaiting client approvalProcurementExpedite supplier / reallocate labour
MCC-Inlet-PUM-04Stores2026-05-14—+5RedAwaiting client approvalBrendan BegleyExpedite supplier / reallocate labour
MCC-Inlet-PUM-04Production2026-06-17—+8RedAwaiting client approvalBrendan BegleyExpedite supplier / reallocate labour
MCC-Inlet-PUM-04Testing (PDI/FAT)2026-07-20—-5Green—Oisin Leonard—
MCC-Inlet-PUM-05Pre Design2026-02-052026-02-06+1Amber—Production ManagerExpedite supplier / reallocate labour
MCC-Inlet-PUM-05Design & Approvals2026-03-082026-03-15+7RedAwaiting client approvalOisin LeonardExpedite supplier / reallocate labour
MCC-Inlet-PUM-05Procurement2026-04-112026-04-18+7RedAwaiting client approvalOisin LeonardExpedite supplier / reallocate labour
MCC-Inlet-PUM-05Stores2026-05-14—-3Green—Procurement—
MCC-Inlet-PUM-05Production2026-06-17—-6Green—M. Henderson—
MCC-Inlet-PUM-05Testing (PDI/FAT)2026-07-20—+6RedAwaiting client approvalOisin LeonardExpedite supplier / reallocate labour
MCC-Inlet-PUM-06Pre Design2026-02-052026-02-050Green—M. Henderson—
MCC-Inlet-PUM-06Design & Approvals2026-03-082026-03-12+4RedAwaiting client approvalM. HendersonExpedite supplier / reallocate labour
MCC-Inlet-PUM-06Procurement2026-04-112026-04-19+8RedAwaiting client approvalM. HendersonExpedite supplier / reallocate labour
MCC-Inlet-PUM-06Stores2026-05-14—0Green—Brendan Begley—
MCC-Inlet-PUM-06Production2026-06-17—-2Green—Brendan Begley—
MCC-Inlet-PUM-06Testing (PDI/FAT)2026-07-20—+6RedAwaiting client approvalOisin LeonardExpedite supplier / reallocate labour
MCC-Inlet-PUM-07Pre Design2026-02-052026-02-06+1Amber—Production ManagerExpedite supplier / reallocate labour
MCC-Inlet-PUM-07Design & Approvals2026-03-082026-03-08-5Green—M. Henderson—
MCC-Inlet-PUM-07Procurement2026-04-112026-04-15+4RedAwaiting client approvalProduction ManagerExpedite supplier / reallocate labour
MCC-Inlet-PUM-07Stores2026-05-14—+8RedAwaiting client approvalM. HendersonExpedite supplier / reallocate labour
MCC-Inlet-PUM-07Production2026-06-17—-1Green—Brendan Begley—
MCC-Inlet-PUM-07Testing (PDI/FAT)2026-07-20—+6RedAwaiting client approvalProcurementExpedite supplier / reallocate labour
MCC-Inlet-PUM-08Pre Design2026-02-052026-02-05-2Green—Brendan Begley—
MCC-Inlet-PUM-08Design & Approvals2026-03-082026-03-10+2Amber—Production ManagerExpedite supplier / reallocate labour
MCC-Inlet-PUM-08Procurement2026-04-112026-04-15+4RedAwaiting client approvalBrendan BegleyExpedite supplier / reallocate labour
MCC-Inlet-PUM-08Stores2026-05-14—+3Amber—Brendan BegleyExpedite supplier / reallocate labour
MCC-Inlet-PUM-08Production2026-06-17—+8RedAwaiting client approvalProcurementExpedite supplier / reallocate labour
MCC-Inlet-PUM-08Testing (PDI/FAT)2026-07-20—+1Amber—Oisin LeonardExpedite supplier / reallocate labour