Battersea Power Station Phase 3
Order · SC-2403

Battersea Power Station Phase 3

Battersea Project Holding · Start 2026-02-01 · FAT 2026-08-18 · Delivery 2026-09-20

Status
active
Contract value
£1.65M
Forecast margin
21.0%
Panels
20
2 switchboards
Stages complete
137/360
9 blocked
Project Hierarchy
Switchboard → Panel Type → Panel → Current Stage. Click a panel to open its lifecycle.
LV-Switch-01
12 panels · 2 types
39%
ACB Incomer · 2/2
MCCB Outgoing · 10/10
Sub-Distribution
8 panels · 1 types
36%
Feeder Panel · 8/8
Delivery Rollup
Avg completion38%
Avg panel health71%
Milestones48
Open risks5
Open issues6
Variations5
Commercial Snapshot
Labour budget£577,500
Labour actual£362,903
Labour variance£214,597
Material budget£742,500
Material actual£657,443
Material variance£85,057
WIP£269,336
Earned progress62%
Procurement (P1–P9)
P1Long Lead Approval Items123/185
P2Steelwork148/198
P3Copper100/216
P4Major Components25/32
P5Labels22/45
P6Cable Identification112/122
P7OEM Equipment64/132
P8Terminals & Wiring Accessories81/139
P9Specialist Items169/211
Quality Gates (QG1–QG7)
QG1Project Handoverpassed
QG2Engineering Releasepassed
QG3Incoming Materials Inspectionpassed
QG4Manufacturing Releasein-review
QG5In-Process Manufacturing Inspectionpending
QG6Pre-FAT Approvalpending
QG7FAT & Shipment Releasepending