Order · SC-2401
Heathrow T2 LV Distribution
Heathrow Airport Holdings · Start 2026-01-08 · FAT 2026-07-15 · Delivery 2026-08-22
Status
on track
Contract value
£2.84M
Forecast margin
18.4%
Panels
23
3 switchboards
Stages complete
179/414
15 blocked
Project Hierarchy
Switchboard → Panel Type → Panel → Current Stage. Click a panel to open its lifecycle.
MSB-01 Main LV Board
11 panels · 3 types
Incomer · 2/2
Bus Section · 1/1
Outgoing Feeder · 8/8
DB-A Distribution
6 panels · 1 types
TPN Feeder · 6/6
DB-B Distribution
6 panels · 1 types
TPN Feeder · 6/6
Delivery Rollup
Avg completion43%
Avg panel health73%
Milestones48
Open risks5
Open issues6
Variations5
Commercial Snapshot
Labour budget£994,000
Labour actual£738,772
Labour variance£255,228
Material budget£1,278,000
Material actual£383,515
Material variance£894,485
WIP£1,509,297
Earned progress50%
Procurement (P1–P9)
P1Long Lead Approval Items28/36
P2Steelwork59/88
P3Copper28/42
P4Major Components102/150
P5Labels69/78
P6Cable Identification82/93
P7OEM Equipment54/62
P8Terminals & Wiring Accessories23/51
P9Specialist Items54/127
Quality Gates (QG1–QG7)
QG1Project Handoverpassed
QG2Engineering Releasepassed
QG3Incoming Materials Inspectionpassed
QG4Manufacturing Releasein-review
QG5In-Process Manufacturing Inspectionpending
QG6Pre-FAT Approvalpending
QG7FAT & Shipment Releasepending